Fertilizers Projects

blog image

Evergrow For Speciality Fertilizers E&I Of Ecophos

Project period : (Apr. '18) to (Till now) Total Man-Hours : In Progress

Owner

Evergrow For Speciality Fertilizers

Client

Evergrow For Speciality Fertilizers

Scope of work

  • Installation and checking of instrumentation & electrical works in new ecophos project.
  • Installation of electrical mv and lv panels.
  • Laying of power and control cables and associated routing such as cable trays and conduits.
  • Installation of lighting system.
  • Installation of earthing system.
blog image

Ammonium Sulphate

Project period : (Oct. '12) to (Jul. '13) Total Man-Hours : 60,000

Owner

Alex Fert Co.

Client

Alex Fert Co.

Scope of work

  • Installation of LV & MV equipments.
  • Cables laying and installation of cable routing system.
  • Supply & installation of earthing of lightening systems.
  • Supply &installation of cable routing system (Trays, Conducts,…….etc).
  • Installation of fire fighting system.
  • Supply &installation of lighting (Fixtures, Boxes……..etc).
  • Installation of low current systems.
  • Pre-commissioning and commissioning works.
  • Installation and checking of instrumentation process connection & final control element.
  • Installation of DCS control system
  • Supply &installation of cable routing system (Trays, Conducts,...etc).
  • DCS/ESD Loop checking.
  • Installation of operating devices(Junction Boxes / Local Cabinets /Air Headers).
  • Installation of cables and associated routing.
  • Function test, pre-commissioning and assistance in commissioning works.
blog image

Misr Oil Processing Company (MOPCO)

Project period : (Mar.’07) To (June.’08) Total Man-Hours : 80,600

Owner

Misr Oil Processing CO.

Client

ThyssenKrupp XERVON

Scope of work

  • Installation and checking of instrumentation process connection & final control element.
  • Installation of control system.
  • DCS / ESD loop checking.
  • Installation of operating devices.
  • Installation of cables and associated routing.
  • Installation of fire alarm & detection system.
  • Function test , pre-commissioning and commissioning works.
blog image

Helwan Fertilizers

Project period : (Jan.’06) to (Dec.’06) Total Man-Hours : 80,000

Owner

Helwan Fertilizers Company

Client

ABB Automation

Scope of work

  • Installation and checking of instrumentation process connection & final control element.
  • Installation of control system.
  • DCS / ESD loop checking .
  • Installation of operating devices.
  • Installation of cables and associated routing.
  • Installation of fire alarm & detection system.
  • Function test , pre-commissioning and commissioning works.
blog image

Egyptian Fertilizers EFC II

Project period : (May.’05) To (May.’06) Total Man-Hours : 70,000

Owner

Egyptian Fertilizers CO.

Client

Orascom Construction Industries, ABB Automation

Scope of work

  • Installation and checking of instrumentation process connection & final control element.
  • Installation of control system.
  • DCS / ESD loop checking.
  • Installation of operating devices.
  • Installation of cables and associated routing.
  • Installation of fire alarm & detection system.
  • Function test, pre-commissioning and commissioning works.
Accurate Team
How can we help you?

17 Abdel Kader Ragab "Green Villa" 3rd floor "Kafer Abdo"
Alexandria - Egypt