ENPPI High Qualified Skilled
Project period : (May. 2025) – in progress
Total Man-Hours : in progress
Owner
Aramco Saudi Arabia
Client
ENPPI
Scope of work
Provision of High Qualified Skilled Electrician and Industrial Fitter
Al-Khushaybi Solar PV Park
Project period : (Jan. 2025) – in progress
Total Man-Hours : in progress
Owner
Saudi Electricity Company
Client
Larsen and Toubro Saudi Arabia LLC
Scope of work
- Low Voltage and solar cable pulling in trenches
- Medium Voltage cable pulling and termination
Rabigh Combined Cycle Power Plant
Project period : (Dec. 2024) – in progress
Total Man-Hours : in progress
Owner
Saudi Electricity Company
Client
El Sewedy Power System Projects – PSP
Scope of work
Cable pulling and termination for the Rabigh project and existing substation, including:
- Medium Voltage cables
- Low Voltage cables
- Fiber Optic cables
- Instrumentation & Control cables
Sulaibiya Waste Water Treatment and Reclamation Plant Extension
Project period : (May. '18) to ( Jul. '20 )
Total Man-Hours : 260,000.00
Owner
Kuwait Ministry of Public Work ( MPW )
Client
Mohamed Abdulmohsin Al-Kharafi & Sons ( MAK )
Scope of work
- Installation of power distribution equipment ( Main power transformer / MV System / LV System /Stand-by power supply system )
- Equipment installation (Cable system / Cable rack & conduit system / Grounding & lightening protection system / Lighting system )
- Control Equipment installation ( Process / Field / Expert / Chemical)
- Instrumentation installation ( Analyzer system / Process system )
- Installation of Electrical systems associated with single machines (storage machines / weigh feeders / hydraulic & lubrication units / deducting filters / cranes, hoists & lifts / cement silos / packing plant / water treatment plant).
- Pre commissioning and Commissioning works
- INSTALLATION AND CHECKING OF INSTRUMENTATION PROCESS CONNECTION & FINAL CONTROL ELEMENT
- INSTALLATION OF CONTROL SYSTEM
- DCS/ESD LOOP CHECKING
- INSTALLATION OF OPERATING DEVICES (JUNCTION BOXES / LOCAL CABINETS / AIR HEADERS)
- INSTALLATION OF CABLES AND ASSOCIATED ROUTING
- FUNCTION TEST, PRE-COMMISSIONING AND ASSISTANCE IN COMMISSIONING WORKS