Power Stations

more than 100,000 man-hour

Beni Swef Power Station ( 2 x 1200MW Combined Cycle )


Total Man-Hours : In Progress

 

From : (Mar. '16) to (Till Now)

Owner : Middle Egypt Electricity Distribution Co.

Client : Power System Projects (PSP)


EEHC 5 X 2 X 25MW Fast, Mobile & Flex. Power


Total Man-Hours : 40,000

 

From : (May. '15) to (Jul. '15)

Owner : Egyptian Electricity Holding Company ( EEHC )

Client : El Sewedy Electric Distribution & Transmission / General Electric (GE)


Attaqa Power Station (2 x 170 MW Simple Cycle)


Total Man-Hours : 250,000

 

From : (Mar. '15) to (Dec. '15)

Owner : East delta electrical production CO.

Client : Power System Projects (PSP)


Banha Power Station (750 MW Combined Cycle)


Total Man-Hours : 87,500

 

From : (Jul. '13) to (May. '14)

Owner : Middle delta electrical production CO.

Client : Ansaldo


Instrumentation calibration Al-Shabab Power station


Total Man-Hours : 10,500

 

From : (Feb.’11) To (Jul.’11)

Owner : West Delta Electricity Production CO.

Client : El-Kharafy National Company

HRSG’S OF 750 MW SIDI KRIR COMBINED


Total Man-Hours : 60,000

 

From : (May.’09) To (Feb.’10)

Owner : West Delta Electricity Production CO.

Client : Project Services CO. (PSC)


NUBARIA POWER STATION 2 x 750 MW GTG


Total Man-Hours : 55,000

 

From : (Feb.’05) To (Aug.’05)

Owner : West Delta Electricity Production CO.

Client : Project Services CO. (PSC)


Talkha POWER STATION


Total Man-Hours : 55,000

 

From : (July.’05) To (June.’06)

Owner : West Delta Electricity Production CO.

Client : Project Services CO. (PSC)